The main steps for the construction of the landfill gas collection and destruction system were the following:
- May 2006: Equipment delivery
 - July to October 2006: Construction
 - Octobre 2006: Commissioning
 - The construction was driven by BioEnergia, one of Biothermica’s subsidiaries
 